Rostov NPP: subject tasks on Unit 3 construction are in good progress under the schedule

08.10.2012
Alexander Hazin , Construction Chief - Director of the Volgodonsk branch of NIAEP, reported on it at the meeting of the construction management board charged for Unit 3&4 construction.
A . B . Hazin marked out that specialists are erecting polar crane in the Unit 3 reactor compartment ( RC ) . He also reported that the grouting of the 85 th tier of the evaporative cooling tower started at an elevation + 136,3 m .
The main topic of the contracting organizations authorities reporting were arrangements on preparations for construction and erection works in winter.
A series of issues on equipment and materials procurement was also discussed, in particular , delivery of large-sized equipment for Unit 3 – steam generator (the third out of four).
Within the meeting issues germane to Unit 4 construction were considered. It was pointed out, that grouting of the circular foundation of the cooling tower is completed as well as grouting of the combined pump station foundation plate in amount of 1659 m3.

Reference:
The merged company JSC NIAEP – JSC Atomstroyexport (ASE) was established in March 2012 by the resolution of the State atomic energy corporation Rosatom. Thus, NIAEP has become a holding company JSC ASE. The structure of the new consolidated company represents a network of offices in charge of construction project management, including: - a design institute in Nizhny Novgorod;- three offices in charge of NPP construction project management (in Nizhny Novgorod, Moscow and St-Petersburg);- representative offices in 10 countries of Europe and Asia where projects are being executed or planned (Bulgaria, Hungary, Vietnam, Iran, India, China, Turkey, Czechia, Slovakia and Ukraine). Today over 4000 people are working for our company; this figure amounts to over 7000 if the personnel of the subsidiaries is included. 20 projects either being under construction or design are now underway in Russia and abroad. List of the power plants under construction and design carried out by the merged company:- Kalinin NPP 4;- Rostov NPP 3 and 4;- Baltic NPP 1 and 2;- Nizhny Novgorod NPP 1 and 2;- Uzhnouralskaya GRES-2 Units 1 and 2;- Tianwan NPP 3 and 4 (China);- Bushehr NPP -1 (Iran);- Akkuyu NPP 1 and 2 (Turkey);- Belarus NPP 1 and 2;- Kudankulam NPP 1 and 2 (India);- Ninh thuan 1 and 2 (Vietnam). Valery Limarenko, doctor of economics, director of JSC NIAEP – holding company JSC ASE. Site of the company: www.niaep.ru


Public relations and information policy department