The Belarusian Nuclear Power Plant has received permit to perform works on the stage-wise program for the power start-up of Unit 1

26.10.2020
On October 23, 2020 the Board of the Ministry for Emergency situations of the Republic of Belarus, based on the resolution of the State Regulatory Authority of the Republic of Belarusian, agreed to amend the licenses of the State enterprise "Belorussian NPP" and JSC ASE EC, allowing to start works based on the stage-wise program for power start-up of Unit 1.

Stage-wise program of the power start-up involves a gradual rise of the reactor power from 1% to 50% and connection of the Unit to the grid at a power level of 40% and dynamic testing at a power level of 50%.Activities performed based on stage-wise program for power start up shall be finished by December, 2020.

Belarusian NPP Unit 1 commissioning started on 7th August, 2020 when the first fuel assembly with fresh fuel was placed into the reactor pressure vessel. On October 11, at the stage of physical start-up, the reactor was brought to the minimum controlled power level (less than 1% of the rated power).In total, more than 50 physical measurements were performed during the physical start-up stage, which confirmed that the nuclear and physical characteristics of the reactor comply with design parameters.

Belarusian NPP with two VVER-1200 reactors having a total capacity of 2400 MW is being constructed in Ostrovets (Republic of Belarus).The Russian 3+ generation design that is fully compliant with the international standards and International Atomic Energy Agency (IAEA) safety recommendations, has been selected for the first NPP in Belarus.
Belarus NPP Unit 1 is the first generation 3+ Unit built abroad based on Russian technologies.Currently, three power Units of similar type have been successfully operating in Russia: two Units at the Novovoronezh NPP and one Unit - at the Leningrad NPP.The fourth generation 3+ power unit - Unit No 6 of Leningrad NPP, was successfully connected to the grid on 22 October. This technology was also selected byFinland, Hungary, Bangladesh, Turkey and Egypt.

Communications Division
Rosatom State Corporation Engineering Division


For reference:
Rosatom State Corporation Engineering Division unites the leading companies of the nuclear industry:ASE EC JSC (Nizhny Novgorod), JSC Atomstroyexport (Moscow), JSC Atomenergoproekt (Moscow) and JSC ATOMPROEKT (Saint-Petersburg) and others.
The Engineering Division is the leader in terms of project portfolio and the number of NPP projects that are constructed abroad simultaneously.
About 80% of the Division's income is accounted for by foreign projects.
The Engineering Division implements design and construction projects for high-power NPPs both in Russia and abroad, it renders a full range of EPC, EPC(M) services including project management and designing and develops Multi-D technologies for management of complex engineering facilities.The Engineering Division is guided by the achievements of the nuclear power industry in Russia and innovative state-of-the-art technologies.
We construct reliable and safe NPPs with III+Gen VVER reactors that are in line with all international requirements and recommendations.
www.ase-ec.ru