Launch of welding works on the main circulation pipeline at the Rostov NPP Unit 4

29.02.2016
On February 29, 2016 at 20:00 p.m. one of the crucial construction milestones, i.e. welding of the main circulation pipeline started in the reactor compartment of the Rostov NPP Unit 4.
The main circulation pipeline (850 mm in diameter, 70 mm thick walls, total length over 130 m) connects the main equipment of the primary circuit: reactor, steam generators and main circulation pumps. The main circulation pipeline is used for circulation of coolant, which is water of 350ºC under pressure of 17,6 MPa.
Four groups of welders of the higher 6th grade will be engaged in the welding works. “Totally, 28 joints must be welded. Schedule of works is approved, each of the 36 welders is assigned with tasks, - marked Alexey Kononenko, Director of the Rostov NPP construction. – Concurrent with the welding works, a step-by-step control of all performed operations will be exerted, i.e. visual, measuring, radiographic, capillary and ultrasonic types of control.
The main circulation pipeline of the Rostov NPP Unit 3 was welded in 143 days. The main circulation pipeline of the Leningrad NPP-2 was welded in 109 days. Welding the main circulation pipeline of the Novovoronezh NPP-2 took 102 days.
For reference:
АSE Group of Companies was established within the framework of development of Rosatom engineering division, by uniting the leading companies of the industry: NIAEP JSC, ASE JSC, Atomenergoproekt JSC and Atomproekt JSC.
ASE is one of the world leaders in nuclear power engineering and holds over 30% of the global NPP construction market.The Group has representative offices, branch offices and operational offices in 15 countries around the world, with almost 80% of its portfolio coming from projects abroad.
ASE also provides services in the field of construction of facilities for RAW and SNF management, thermal power plants as well as a full range of EPC, EPC(M) and PMC services for any complex engineering facilities.
ASE has developed and widely uses Multi-D innovative project management system for construction of complex engineering facilities which enables to effectively manage such parameters as the budget, the construction period and the quality. The company President is Valery I. Limarenko, PhD in economics.