Specialists started to load dummy fuel assemblies at Unit 1 of Belarus NPP

23.04.2019
Specialists started to load dummy fuel assemblies (dummy FAs) into the reactor at Unit 1 of Belarus NPP (General Contractor and General Designer — ASE, Engineering Division of Rosatom State Corporation). This is one of the most important processes at the stage of the reactor plant preparation for the cold and hot run stage.

Dummy FAs are exact copies of fuel assemblies, entirely repeat their structure, but do not contain nuclear fuel. They are used instead of standard FAs during start-up and adjustment works at the cold and hot run stage of the reactor plant.

“Start of dummy FA loading is an evidence of readiness for the systems and equipment intended for nuclear fuel treatment during the power unit operation, for check of compliance with design parameters and safety requirements”, said Vitaly Polyanin, Vice-President — Director of Belarus NPP Construction Project, ASE EC JSC. — After the loading of all 163 FA in the reactor is completed, a small scope of works will remain concerning its final assembly for the stage of hydraulic testing and circulation washing of equipment in the primary and secondary circuits of the reactor plant. Its start is scheduled for the end of May".

Belarus NPP with two reactors of VVER-1200, total capacity is 2400 MW, is constructed based on the Russian design of 3+ Generation, which fully corresponds to international standards and recommendations of the International Atomic Energy Agency (IAEA).

For information:

ASE (Rosatom State Corporation Engineering Division) was established by integration of the leading companies of the industry: ASE EC JSC (Nizhny Novgorod), Atomstroyexport JSC (Moscow), Atomenergoproekt JSC (Moscow) and ATOMPROEKT JSC (St. Persburg).

ASE is one of the global leaders in nuclear power engineering holding about 30% of the global NPP construction market. The Engineering Division operates in Europe, Middle East and North Africa, Asia and Pacific.

Foreign projects account for over 80% of the portfolio.

It implements design and construction projects for high-power NPPs, renders a full range of EPC, EPC(M) services and develops Multi-D technologies for management of complex engineering facilities.

The Engineering Division draws on lessons learned from over the 50-year history of the nuclear power industry in Russia and state-of-the-art technologies.

We construct reliable and safe NPPs with 3+Gen VVER reactors that are in line with all international requirements and recommendations.

www.ase-ec.ru

Contact details:

Head Office:

Address: 3, Svobody Square, Nizhny Novgorod, 603006, Russia

Phone: +7 (831)421-79-00

Moscow Branch office:

Address: 2, Bld. 1, Dmitrovskoye Shosse, Moscow 127434, Russia

Phone: +7 (495)737-90-37

E-mail: niaep@ase-ec.ru